|

Preliminary
After the contracts are
signed, we will create a
plot plan of your lot
showing the location of the
house on the property. The
building plans will be
submitted to the developer
or architectural committee
for their approval. Other
plans will be submitted to
the appropriate township
permit office with our
application for a building
permit. The banks will
require building plans and
specifications for a
property appraisal prior to
loan closing. Also at this
time we will order windows,
doors and brick. It is not
unusual for these processes
to take 3-4 weeks
Foundation
This stage begins with the
creation of a level pad
site. Pad elevation is very
critical in insuring proper
water drainage away from the
structure. Next, the house
is staked out on the lot in
accordance with the plot
plan and the footing is dug.
Steel bars are installed in
and up through the footing.
A city inspector will
approve the footing prior to
pouring any concrete. After
the footing is poured, wood
forms will be erected around
the perimeter of the
structure. These forms
determine building size and
finished floor elevation,
another critical step in
insuring proper drainage.
Rough-In's
After the forms are in place
on the footing, plumbers
will rough in all water and
drain lines. We use only
copper water lines and PVC
drain pipes. The plumbers
will run the main water,
sewer and gas lines to the
appropriate tie in locations
at this time. Upon the
plumber's completion and
city inspection, fill dirt
is brought in and installed
inside the wood forms and
leveled off approximately 4"
below the tops of the forms.
If the heat and air ducts
are to be installed under
the slab they are installed
at this time and inspected.
Next, post tension cables
are installed and the steel
bars extending from the
footing are bent over into
the slab area to tie the
full footing and slab
together. The footing is
cleaned to insure proper
placement of concrete and
the full structure treated
for termites then another
city inspection is done
prior to pouring any
concrete. Upon inspection,
the slab is poured and the
forms removed. Seven to ten
days after the slab is
poured the post tension
cables are tightened to
28,000 pounds of pressure
per square inch and cut
flush with the slab.
Exterior
Once the slab is poured,
carpenters will begin the
framing process. During this
stage you will see
substantial progress very
quickly. Walls, headers,
beams, floor trusses and
rafters are engineered to
assure proper structural
properties throughout the
dwelling. Many interior
items and changes are left
until the final stages of
the framing process called
"punch out". Windows, doors
and fireplaces are installed
and cabinets ordered at this
time. Brick ties are nailed
on all surfaces that will
receive masonry to insure
that these walls are held
tightly to the framing.
Roofing shingles are applied
and the house is "in the
dry".
Mechanical
After the roof is on,
plumbers return for their
"top out". This is when they
run additional water and
drain lines as well as vent
pipes and gas lines. They
also install certain tubs
and showers at this time.
All lines are pressurized to
protect against possible
leaks later on.
The furnaces are set and the
ductwork run throughout the
house. Provision is made for
return airflow to the
furnaces and air handler and
also for the condensing
units, which shall be
installed outside later on.
Bathroom fans are vented to
the exterior at this time.
The electricians will rough
in the wiring for the
breaker box, switches,
receptacles, and lights.
Heavy gauge wire will be run
for the cooking equipment
and air conditioners.
Recessed light fixtures are
installed at this stage, as
are your cable TV and
telephone outlets.
All mechanical trades will
have their rough in work
inspected and then a frame
inspection is done to make
sure no boards have been cut
or moved that could cause
structural weakness. Upon
all approvals, insulation is
installed in the walls that
will be insulated and
certain inaccessible
ceilings. All holes in
exterior walls are filled
with polycell foam to
maintain air tightness.
Exterior masonry is normally
installed about this same
time. All interior
selections and colors must
be finalized at this point.
Drywall/Trim/Painting
Sheetrock is installed on
all ceilings and walls then
taped, bedded and skimmed.
Wall texture is applied if
applicable. Hardwood floors
are installed next by first
laying plastic over the
concrete slab then
installing 5/8" plywood to
the concrete. A layer of 15
pound felt tops the plywood
and finally true hardwood
floors are installed
thereon. Trim carpenters
arrive to install the
cabinets, doors, moldings
and mantle. Your closets are
laid out and installed to
maximize their storage
capacity. Painters take over
and initially stain any
necessary wood and then
apply oil-based enamel to
all other woodwork.
Afterwards these surfaces
are tightly taped and the
walls and ceilings painted.
Exterior landscaping, sod
installation, guttering and
the pouring of concrete
driveways, sidewalks and
porches may take place now
or as weather permits.
Interior
Finish
Kitchen and bathroom
countertops and marble tubs
and showers are installed as
well as ceramic tile floors
and backsplash. Then
plumbers will install
fixtures and faucets. Next,
electricians install light
fixtures, switches and
receptacles, and appliances.
Finally, garage door
openers, security keypads,
shower doors, mirrors and
hardware complete
construction prior to the
installation of carpeting
and putting the final coat
on the hardwood floors.
Final Detailing
After the carpets are in, a
detailed cleaning takes
place to get your home in
move in condition. Window
screens are installed and
final inspections take
place. Your pre-closing walk
thru will take place at this
time.
After Closing
You should make special note
to file for homestead
exemption on you property
taxes. This can be done as
soon as you receive your
recorded deed back from the
mortgage company at the
county courthouse. |